Buyer’s guide
Building a house on a plot in Georgia: permits and timelines
A private house belongs to construction class II and needs a permit from the municipality. It is issued in two stages: first the development conditions (10 working days), then the permit itself (20 working days). You can only build on non-agricultural land.
Step 0. Land category
A house is built on non-agricultural land. If the plot is agricultural, its category is changed first — see the guide “Can you change land from agricultural to non-agricultural in Georgia?”.
Five construction classes
The Spatial Planning Code divides all buildings into five classes by level of risk (art. 96).
- Class I — the simplest structures. No permit is needed; notifying the municipality is enough (art. 94(1)).
- Class II — this includes an individual house (art. 120(4)). A permit is needed. The municipal Sakrebulo may decide to replace it with a detailed notice (art. 94(3)), so the procedure depends on the area.
- Classes III and IV — large buildings. A permit is needed (art. 94(2)).
Who issues the permit
The executive body of the municipality — the city hall of the area where the plot is located (art. 100).
Stages and timelines
- Development conditions. The municipality approves what can be built on the plot and to what parameters. Deadline: 10 working days (art. 104(2)).
- Building permit. The design is submitted and the municipality issues the permit. Deadline: 20 working days (art. 107(3)).
If the applicant prefers, the procedure can run in three stages: the architectural design is approved separately (17 working days, art. 108(3)), and the permit itself is then issued within 5 working days (arts. 102, 108).
If the municipality does not respond in time, the decision is deemed positive (arts. 104(7), 107(7)).
What we do
Before you buy, we find out which development parameters apply to the plot, so you know what kind of house you can build there. We select plots to fit your project. Our services are free for clients.
Quick answers
- How long does the whole process take?
- By the legal deadlines, about 30 working days for the two stages, not counting the time to prepare the design.
- Do I need a permit for a sauna or a gazebo?
- Simple class I structures are built on notice, without a permit. Which class a particular structure belongs to is best confirmed with the municipality.